What a 250 TPH crusher plant really produces in a day and a month

By Ashok Kumar4 min read

The short answer

TPH is tonnes per hour through the feed end with everything running. A 250 TPH plant on two shifts does not make 250 x 16 x 30 tonnes a month. After working days, stoppages inside the shift, product mix, weather and the pace at which the road can take material, plan on 25,000 to 30,000 tonnes a month, or roughly 1,000 to 1,150 tonnes a working day.

The rating plate on a crusher plant is a true figure about a narrow thing. It says what the primary can take in an hour when the feed is well broken, the rock is of average hardness and nothing downstream is holding it back. A programme built on that number multiplied by the calendar will be short by the end of the first quarter.

01From nameplate to dispatch

StepAllowanceTonnes a month
Nameplate x clock250 TPH x 16 h x 30 days120,000
Working days26 of 30104,000
Hours actually crushing11 of 1671,500
Feed rate on graded road productsAbout 60% of nameplate42,900
Weather, breakdowns, liner changesAbout 15% lost36,500
What the site can take and stockLaying fronts, yard space, tippers25,000 to 30,000
Table 01 · Where the tonnes go: a 250 TPH plant on two eight-hour shifts

The allowances are planning figures from our own plants. A dry season on an easy rock with a hungry road will beat them. A monsoon month will not come close.

02What each line is

Hours actually crushing

A sixteen-hour day loses time at both ends of each shift, at meals, during the daily greasing and inspection round, and every time the quarry clears for a blast. It also loses time waiting for rock. The plant can only crush what the excavators and tippers put in the hopper, and a face that is behind on drilling starves it.

Feed rate on graded products

The nameplate assumes a coarse product. Road gradings ask for a good share of 20 mm, 10 mm and fines, which means stone going round the secondary and tertiary circuit more than once. Every tonne that recirculates takes the place of a new tonne at the feeder. Harder rock slows it further, and a tight closed side setting slows it again. The machines behind this are described in jaw, cone and VSI.

What the site can take

This is the line nobody puts in a brochure. A plant on a highway package makes stone for a road that is being built in fits and starts. Laying waits on land, on bitumen, on approvals and on weather. When the fronts are not taking material the yard fills, and a full yard stops the plant as surely as a broken belt. The plant's month is set by the road's month.

03Sizing a plant for a package

Work back from the total stone the package needs and the months in which it can really be produced. Leave out the monsoon months and the mobilisation month, then compare what is left with a realistic monthly figure.

Total stone required
9,00,000 t
Construction period
30 months
Less mobilisation and two monsoons
7 months
Effective producing months
23
One 250 TPH plant at 27,500 t a month
6,32,500 t
Required rate
39,100 t a month
Worked example · A package needing 9 lakh tonnes of crushed stone over a 30-month construction period

One 250 TPH plant falls about 2.7 lakh tonnes short. The choices are a larger plant, a second plant for the peak, a third shift through the dry season, or buying in the balance. Each has a cost and a lead time, and all of them are cheaper to arrange at award than in month fourteen.

04A third shift is not fifty per cent more

Running round the clock adds eight scheduled hours. It also removes the gap in which maintenance was being done. Liners still wear, belts still need tracking, screens still need changing, and now each of those stops the plant during production instead of between shifts. A third shift is a good answer for a few dry months and a poor one as a standing plan.

Asked on the back of this

01What does TPH mean on a crusher plant?

Tonnes per hour. It is the rate at which the plant can accept feed under good conditions, not a guarantee of finished product per hour over a month.

02How many tonnes does a 250 TPH plant make in a day?

On two shifts making road gradings, about 1,000 to 1,150 tonnes of dispatched material on a working day averaged over a month. Individual dry-season days run well above that, and wet days well below.

03How many tippers does that keep busy?

At 18 tonnes a load, 1,100 tonnes is about sixty trips a day out of the plant. The fleet needed to make those trips depends on the lead distance.

Get a rate

Need a plant on your site?

Enough to price the job properly, and enough to say honestly if we cannot take it. Send it before 6pm and you will hear back the same day.

01
Location
and the lead to the road head
02
Grading
GSB, WMM, 40 / 20 / 10mm
03
Tonnage
a month, not in total
04
Start date
and how firm it is

Not ready for a rate? The questions buyers ask cover capacity, how long mobilising takes, leases and how billing works.

Read those first

Or call +91 93093 43222 · Monday to Saturday, 9am to 6pm

+91 93093 43222WhatsApp