Crushing rate per tonne: what is inside the figure and what is not

By Subhash Pachar4 min read

The short answer

A per-tonne crushing rate normally covers the plant, its erection, the operating crew, routine maintenance and wear parts. It normally leaves out the rock, royalty, electricity or generator diesel, and the land. The rate falls as the monthly tonnage rises, and it climbs with harder rock, a finer product mix and a tighter grading.

Two crushing rates that differ by a few rupees a tonne are often quotes for different scopes. Before comparing the figures, compare the lists underneath them.

01Inside and outside

ItemUsuallyWhy it varies
Plant, structure and conveyorsInsideIt is the contractor's asset
Transport and erectionInside, or as a mobilisation advanceLong moves and short contracts get it priced separately
Operators, fitter, electricianInsideThey arrive with the plant
Jaw plates, cone liners, screen mesh, beltsInsideAbrasive rock raises the allowance
Loader feeding the hopper and stockpilingEitherDepends on whose machines are already on site
Shot rock delivered to the hopperOutside, unless mining is in the scopeDrilling, blasting and haulage are a separate rate
Electricity or generator dieselOutside, or reimbursed at costGrid supply is cheaper and not always available
Royalty and transit passesOutsideThey follow the lease holder
Land, approach road, waterOutsideThey belong to the site
Testing at an outside laboratoryOutsideThe contract names the laboratory
Table 01 · What a per-tonne crushing rate usually carries

02Five things that move the rate

Monthly tonnage

A plant and its crew cost nearly the same whether they make 15,000 tonnes in a month or 30,000. Spread over twice the tonnes, that fixed cost halves. This is the single largest lever, and it is why a contractor asks for the monthly figure and not the total.

The rock

Hard, abrasive stone eats manganese. Liners that last months in limestone last weeks in quartz-rich granite, and each change costs steel and a shift. Hard rock also passes through more slowly. Both effects end up in the rate, which is why a sample or a site visit comes before a figure.

The product mix

A plant making mostly GSB is doing easy work. One making mostly 10 mm and dust is sending stone round the circuit two or three times. The same machine may produce a third fewer tonnes in the hour, and the rate per tonne moves with it.

The length of the job

Dismantling, moving and erecting a plant costs the same for a six-month job as for a thirty-month one. On a short contract that cost is a large share of every tonne. Mobilisation is usually shown as its own line for that reason.

The feed

A crusher fed with well-fragmented rock at a steady rate runs near its rating. One fed with boulders and gaps does not. If the drilling, blasting and haulage sit with a different firm, expect the crushing contractor to ask for a maximum feed size and a minimum tonnage at the hopper, because without them the output is not theirs to promise.

03The clauses that matter more than the rate

  • Minimum offtake. The monthly tonnage you undertake to accept, and what happens in a month you cannot.
  • Escalation. Whether the rate moves with the price of diesel, and by what formula.
  • Measurement. Weighbridge at dispatch, with dockets, or a stockpile survey. Dockets end arguments that surveys start.
  • Grading. The table the stone must meet, the laboratory that decides, and who bears a rejected stockpile.
  • Idle time. Who pays when the plant is ready and the site is not.
  • Demobilisation. How much notice ends the contract and who clears the yard.

04What to send for a real figure

Four things are enough to price a job properly: where the site is and how far the plant stands from the road head, the gradings required, the tonnes needed each month, and the start date with an honest view of how firm it is. Add the rock type if you know it and a note on whether grid power reaches the site.

Asked on the back of this

01Does the crushing rate include GST?

Rates are normally quoted before GST, with the tax shown as a separate line on the invoice. Ask for the basis in writing so that two quotes are compared like for like.

02Why does the contractor want a minimum quantity?

Because a plant and its crew are committed to your site whether or not you take material. The minimum protects that commitment in a slow month. In exchange you get a rate that reflects the full tonnage.

Get a rate

Need a plant on your site?

Enough to price the job properly, and enough to say honestly if we cannot take it. Send it before 6pm and you will hear back the same day.

01
Location
and the lead to the road head
02
Grading
GSB, WMM, 40 / 20 / 10mm
03
Tonnage
a month, not in total
04
Start date
and how firm it is