Drilling and blasting cost per cubic metre: how the rate is built

By Subhash Pachar4 min read

The short answer

A drilling and blasting rate is three costs added together: metres drilled per cubic metre of rock, explosive and initiation per cubic metre, and the fixed cost of licences, magazine, crew and monitoring spread over the monthly volume. Rock hardness, hole diameter and the distance to the nearest building move the figure far more than any contractor's margin does.

Nobody can give an honest rupee figure for drilling and blasting without seeing the face, and anybody who does is quoting an average. What can be set out is how the figure is assembled, so that two quotations can be taken apart and compared line against line.

01The three parts of the rate

Cost headPhysical quantityWhat pushes it up
Drilling0.08 to 0.15 m drilled per m3 in production benchesSmall holes, hard or abrasive rock, low benches, tight patterns
Explosive0.25 to 0.6 kg per m3 in most quarry rockHard massive rock, small fragment size, wet holes needing cartridged product
InitiationOne detonator and booster per hole, plus surface delaysMore holes per cubic metre, delay-by-delay timing near structures
Fixed site costMagazine, van, licensed crew, monitoring, surveyLow monthly volume to spread it over
Table 01 · What a drilling and blasting rate is made of

Ranges are typical of quarry and highway rock cutting. A particular face can sit outside them.

The first two rows are set by the pattern. Burden, spacing and bench height decide how much rock each metre of hole breaks, as worked through in reading a drilling pattern. Explosive per cubic metre is the powder factor, which has its own article.

02Solid, loose or tonnes

Before comparing rates, check the unit. The same job can be paid three ways, and the numbers look nothing alike.

UnitHow it is measuredEquivalent
Cubic metre in the solid (bank)Survey levels before and after1.00 m3
Cubic metre looseTipper body or stockpile surveyAbout 1.5 to 1.6 m3
TonneWeighbridgeAbout 2.6 to 2.9 t, by rock type
Table 02 · The same rock measured three ways

A rate per loose cubic metre should be roughly two-thirds of the rate per solid cubic metre for the same work. A contract that does not say which is meant will be argued over at the first bill. Tonnes over a weighbridge are the hardest to dispute, and that is how we prefer to be measured.

03Why controlled blasting costs more

Close to buildings, a road or a pipeline, the charge that may be fired on any one delay is capped by the vibration limit. The blaster responds with smaller holes on a tighter pattern, more delays, shorter rounds and sometimes covering over the shot. Each of those adds drill metres, detonators or shifts for the same volume. The rate per cubic metre goes up, sometimes steeply.

It is still the cheap option. The alternatives are breaking the rock mechanically at several times the cost, or being stopped by the district administration after a complaint. Our Western Bhopal Bypass package is drilling and blasting only, with housing close to the alignment, and on a job like that the charge per delay decides the programme.

04What usually sits outside the rate

  • Secondary breaking of oversize, unless a fragment size has been guaranteed.
  • Vibration monitoring and the pre-blast survey of nearby buildings, where a consultant asks for a third party.
  • The explosives magazine and van, where the client's licence is being used instead of the contractor's.
  • Royalty on the mineral and any transit pass, which follow whoever holds the lease.
  • Dewatering of wet benches, and the waterproof explosive that wet holes need.
  • Standing time when the shot is ready and the site cannot be cleared.

05Taking two quotations apart

Ask each bidder for the pattern their rate assumes: hole diameter, burden, spacing, bench height and powder factor. A low rate built on a wide pattern is a low rate for boulders. Ask what fragment size they will stand behind, expressed against the feed opening of the crusher. Ask who pays for the breaker when the shot does not deliver it.

Then ask whose licence the explosive moves under and who the shotfirer is employed by. The cheapest rate on the sheet is often the one that has left those two answers vague. What our own rate carries is set out under controlled blasting and drilling.

Asked on the back of this

01Is drilling and blasting paid per cubic metre or per tonne?

Either. Highway rock cutting is usually measured per cubic metre in the solid from survey levels. Quarry production is more often paid per tonne over a weighbridge. The two convert at the density of the rock, typically 2.6 to 2.9 tonnes per solid cubic metre.

02Why do two contractors quote very different rates for the same rock?

Usually because they have assumed different patterns. A wider pattern needs fewer metres and less explosive, and it produces coarser rock. Unless both quotes state the fragment size they will deliver, they are not prices for the same thing.

Get a rate

Holes to drill on a live bench?

Enough to price the job properly, and enough to say honestly if we cannot take it. Send it before 6pm and you will hear back the same day.

01
Location
and the lead to the road head
02
Grading
GSB, WMM, 40 / 20 / 10mm
03
Tonnage
a month, not in total
04
Start date
and how firm it is