Powder factor: formula, typical values and the false economy of a low one

By Ashok Kumar4 min read

The short answer

Powder factor is the weight of explosive used to break a unit of rock. Divide the kilograms of explosive in a hole by burden x spacing x bench height to get kilograms per cubic metre. Quarry bench blasting typically runs from about 0.25 kg/m3 in soft rock to 0.6 kg/m3 or more in hard, massive rock. Many Indian quarries quote the inverse instead: tonnes of rock broken per kilogram.

Powder factor is the first number anybody asks about a blast and one of the least informative on its own. It tells you how much explosive was used. It does not tell you where in the rock it was.

01The formula

Hole length including 0.9 m sub-drill
8.9 m
Less stemming
2.5 m
Charged length
6.4 m
ANFO in a 110 mm hole at 0.85 g/cc
8.1 kg per metre
Charge per hole
52 kg
Rock per hole: 3.0 x 3.5 x 8.0
84 m3
Powder factor
0.62 kg/m3
Worked example · 110 mm hole, 8 m bench, 3.0 x 3.5 m pattern, ANFO

At a rock density of 2.7 tonnes per cubic metre that is 0.23 kg per tonne. Turned upside down it is 1.6 cubic metres per kilogram, or 4.4 tonnes per kilogram. All four describe the same blast.

02Two conventions, opposite directions

Textbooks and most specifications give powder factor as kilograms per cubic metre, where a higher number means more explosive. On many Indian quarry floors it is spoken of as tonnes per kilogram, where a higher number means less explosive. A manager who says the powder factor has gone up may mean the blast was heavier or lighter. Ask for the unit before agreeing that it is good news.

03Typical values

Rockkg per m3kg per tonneTonnes per kg
Soft: weathered sandstone, shale, soft limestone0.15 to 0.300.06 to 0.138 to 16
Medium: sound limestone, sandstone, softer basalt0.30 to 0.450.11 to 0.176 to 9
Hard: granite, dense basalt, quartzite0.45 to 0.700.17 to 0.264 to 6
Table 01 · Typical powder factors for quarry bench blasting

For production benches feeding a crusher. Massive unjointed rock sits at the top of its range, closely jointed rock at the bottom.

04What the figure hides

Two blasts with the same powder factor can produce very different muckpiles. Take 0.4 kg per cubic metre delivered through 165 mm holes on a 5 by 6 m pattern, and the same 0.4 delivered through 76 mm holes on a 2.3 by 2.8 m pattern. The second puts a charge within two metres of every piece of rock. The first leaves blocks nearly four metres from the nearest explosive. The fragmentation will not be alike.

Distribution up the hole matters in the same way. A long stemming column means the top third of the bench has no explosive in it, whatever the average says. This is the usual source of the slabs described in oversize at the hopper.

05The false economy

Explosive is a visible cost with an invoice every week, so it attracts attention. Opening the pattern a little cuts that invoice and the drilling bill at the same time. The saving is real and it is immediate.

The cost arrives later and under other headings. Coarser rock digs more slowly, so loading cost per tonne rises. More of it needs a breaker. The primary crusher works harder on every piece and passes fewer tonnes an hour, and its liners wear sooner. Each of those is larger per tonne than the explosive saved, and none of them is on the blasting sheet.

The reverse error exists as well. Too much explosive throws rock, damages the wall behind the shot and turns good stone into excess fines that nobody ordered.

06Finding the right figure for a face

  1. Start from the middle of the range for the rock type, with the pattern set from the hole diameter.
  2. Record for each blast: powder factor, breaker hours on the muckpile, excavator loading rate, and crusher tonnes per hour on that rock.
  3. Change one thing at a time, by a small step.
  4. Stop when the total cost per tonne at the stockpile stops falling. That figure, not the lowest powder factor, is the one to hold.

It takes a firm that sees both ends to do this, which is the practical argument for giving drilling, blasting and crushing to one contractor. The pattern side is in reading a drilling pattern.

Asked on the back of this

01How is powder factor calculated?

Total explosive in kilograms divided by the volume of rock broken in cubic metres. For one hole, the rock volume is burden multiplied by spacing multiplied by bench height.

02What is a good powder factor?

There is no single good value. It depends on the rock and on what the broken rock is for. For crusher feed, the right figure is the one that gives the lowest total cost of drilling, blasting, loading and crushing together.

Get a rate

A shot to fire near something that matters?

Enough to price the job properly, and enough to say honestly if we cannot take it. Send it before 6pm and you will hear back the same day.

01
Location
and the lead to the road head
02
Grading
GSB, WMM, 40 / 20 / 10mm
03
Tonnage
a month, not in total
04
Start date
and how firm it is