Moving a crusher plant between sites: what the relocation involves

By Subhash Pachar4 min read

The short answer

Relocating a fixed crusher plant is three jobs: dismantling it into trailer loads, moving those loads across state lines, some of them over-dimensional, and erecting and commissioning at the far end. The road leg is usually the shortest part. From the last tonne at the old site to steady production at the new one, allow about a month where access is reasonable: two weeks to move, two to erect and commission.

A crusher plant earns nothing between packages. The faster it gets from the yard it has finished in to the yard it is needed in, the more of its life it spends making stone. Most of what slows a move is decided before the first bolt is undone.

01What comes apart

A three-stage plant breaks down into the crushers themselves, the vibrating feeder and hopper, three or four screen boxes, a dozen or more conveyors, the supporting steel, the control cabin and electrical panels, and the weighbridge. Conveyors and structure go on ordinary flatbeds. The jaw crusher, the cone and the larger screens are the heavy or awkward pieces and travel on low-bed trailers.

Good dismantling is half of good erection. Match-mark every joint, bag and label the fasteners, photograph the wiring before disconnecting it, and load in the reverse of the order things will be needed. A plant stripped in a hurry arrives as a puzzle.

02Over-dimensional loads

The Central Motor Vehicles Rules cap a goods vehicle and its load at 2.6 m wide. Height is 4.0 m in general and up to 4.75 m for construction equipment and indivisible loads. Length is 12 m for a rigid truck and 18.75 m for a truck and trailer. A screen box or a crusher frame that exceeds any of these on its trailer is over-dimensional cargo and needs permission before it moves.

For national highways that permission is applied for on the Ministry of Road Transport and Highways' online portal for over-dimensional and over-weight cargo. State roads along the route need their own clearance. Allow for it in the programme, and decide early whether a wide piece is better carried whole under a permit or split into legal loads and reassembled.

03The route

  • Bridges and culverts with a posted weight limit below the loaded trailer.
  • Overhead lines and underpasses lower than the load.
  • Villages where the road narrows to less than the trailer's swept path.
  • Hill sections with hairpins a long trailer cannot take.
  • State border check posts, and the documents each one asks for.
  • The last kilometre into the new site, which is nearly always the worst.

Somebody should drive the route before the trailers are booked. A bridge discovered with a 60 tonne load already on the approach is a week lost.

04The far end starts first

Foundations at the new site should be cast and gaining strength while the plant is still being dismantled at the old one. If the trailers arrive to bare ground, the plant waits on concrete. The same goes for the approach road, the level standing, the power arrangement and the consents: everything in setting up a stone crusher plant has to be ready before the steel is.

05A timeline

StageWhat happensAllow
Before the moveRoute check, permits, foundations cast at the new siteRuns alongside the last weeks of production
Dismantle and moveStrip, load, travel, unload, plus machines and crewAbout two weeks
ErectStructure, crushers, screens, conveyors, cablingMost of two weeks
CommissionDry run, feed, grading trials, weighbridge stampingThe last few days of those two weeks
Table 01 · A typical relocation, where access is reasonable

Hill terrain, a monsoon start or a weak approach road adds to every row.

06What gets forgotten

  • The weighbridge has to be re-verified by Legal Metrology after it is moved. Until it is stamped, its slips are not valid for trade.
  • Consent to Operate belongs to a location. The new site needs its own.
  • Wear parts. Moving is the cheapest moment to fit new liners and screen mesh, with everything already open.
  • The crew. People move with the plant or they are replaced by people who have never run it.
  • The old site. Foundations, scrap and stockpile bottoms have to be cleared before the land is handed back.

Standards and rules referred to

  • Central Motor Vehicles Rules, 1989, Rule 93: overall dimensions of motor vehicles.
  • Ministry of Road Transport and Highways: online permission system for over-dimensional and over-weight cargo.

Clauses are quoted as a working reference. Your contract and the revision it names govern, so check the figure against the document on your own site before building to it.

Asked on the back of this

01How long does it take to shift a crusher plant?

About a month from stopping at one site to steady production at the next where access is reasonable: roughly two weeks to dismantle and move, and two weeks to erect and commission. Permits and foundations at the new site must be ready in advance.

02What is ODC in transport?

Over-dimensional cargo: a load that exceeds the width, height or length permitted for a goods vehicle under the Central Motor Vehicles Rules. It may move only with prior permission and under the conditions of that permission.

Get a rate

Stone or plant that has to move?

Enough to price the job properly, and enough to say honestly if we cannot take it. Send it before 6pm and you will hear back the same day.

01
Location
and the lead to the road head
02
Grading
GSB, WMM, 40 / 20 / 10mm
03
Tonnage
a month, not in total
04
Start date
and how firm it is

Not ready for a rate? The questions buyers ask cover capacity, how long mobilising takes, leases and how billing works.

Read those first

Or call +91 93093 43222 · Monday to Saturday, 9am to 6pm

+91 93093 43222WhatsApp