Shri Krishan Construction India Pvt Ltd

Bank, loose and compacted: why earthwork quantities never match

By Subhash Pachar4 min read

The short answer

Soil and rock change volume as they are handled. One cubic metre in the ground becomes about 1.25 cubic metres in a tipper for ordinary earth and 1.5 to 1.6 for blasted rock. Compacted into an embankment, that same cubic metre of earth ends up as roughly 0.9. The bill of quantities pays in one state and the trucks carry another, so convert before counting loads.

Three people on one job can each be right about the quantity and each have a different number. The surveyor measured the cutting before it was dug. The transport clerk counted tipper loads. The engineer measured the finished embankment. They were measuring the same material in three states.

01The three states

  • Bank. Undisturbed, as it lies in the ground. Cutting and rock excavation are measured here, from levels taken before and after.
  • Loose. Dug or blasted and sitting in a bucket, a truck or a heap. Broken material has air between the pieces, so it takes up more room.
  • Compacted. Placed in layers and rolled to the specified density. Embankment and subgrade are measured here.

02Typical factors

MaterialLoose, m3Compacted, m3Bank density, t/m3
Sand and gravel1.10 to 1.150.95 to 1.001.7 to 1.9
Ordinary earth, loam1.20 to 1.300.85 to 0.901.6 to 1.9
Clay1.30 to 1.400.85 to 0.901.7 to 2.0
Weathered rock, ripped1.30 to 1.451.05 to 1.202.0 to 2.4
Hard rock, blasted1.50 to 1.651.25 to 1.402.6 to 2.9
Table 01 · Volume of one bank cubic metre after digging and after compaction

Planning values. The compacted figure for earth depends on how dense the ground was to begin with: loose natural soil shrinks more, dense soil less. Test your own material before fixing a rate on it.

The pattern to remember is that earth ends up smaller than it started and rock ends up larger. A cubic metre of soil cut from a hillside fills about 0.9 of a cubic metre of embankment. A cubic metre of rock from the same cutting fills 1.3. A mass haul diagram that treats them alike will be out by a third.

03From BOQ to loads

Compacted volume in the BOQ
10,000 m3
Bank volume to dig, at 0.90
11,100 m3
Loose volume to haul, at 1.25
13,900 m3
Weight, at 1.8 t/m3 in the bank
20,000 t
Loads by volume, 14 m3 body
993
Loads by weight, 18 t payload
1,111
Worked example · An embankment of 10,000 m3 compacted, built from borrow earth

Both limits apply and the larger number of loads is the real one. Here the truck reaches its legal weight before its body is full, so weight governs. With a light, dry soil it can go the other way. Price the haulage on whichever is higher. Fleet sizing from that load count is in how many tippers a job needs.

04What the contract actually pays for

On highway work, embankment and subgrade are paid as compacted volume, measured from cross-sections of the finished layer. Borrow excavation is normally not paid separately. So the contractor is paid for 10,000 cubic metres and has dug, hauled, spread, watered and rolled 11,100. A rate built on the BOQ figure alone has left out a tenth of the work.

Cutting is the reverse. It is paid in the bank, and what leaves in trucks is a quarter to two-thirds more volume than the paid figure. Nobody is being cheated in either case. The rate simply has to be built in the unit the bill uses.

05Where the factors go wrong

  • Assuming one factor for a whole cutting. Most cuttings pass from soil through weathered rock into hard rock, and each band behaves differently.
  • Wet season moisture. Wet clay weighs more per load and may be unusable as fill until it dries.
  • Rock in fill. Blasted rock placed as embankment leaves voids unless it is graded and the voids are filled, which is why specifications limit lump size and layer thickness.
  • Topsoil. Stripped separately, stockpiled and re-spread. It is not embankment and should not be in the balance.

Asked on the back of this

01What is the bulking factor of soil?

The increase in volume when soil is dug. Ordinary earth swells by about 20 to 30 per cent, clay by 30 to 40 per cent, and blasted hard rock by 50 to 65 per cent.

02What is shrinkage in earthwork?

The reduction in volume when excavated soil is compacted into fill at a density higher than it had in the ground. For ordinary earth it is typically 10 to 15 per cent of the bank volume.

Get a rate

A formation to hand over at level?

Enough to price the job properly, and enough to say honestly if we cannot take it. Send it before 6pm and you will hear back the same day.

01
Location
and the lead to the road head
02
Grading
GSB, WMM, 40 / 20 / 10mm
03
Tonnage
a month, not in total
04
Start date
and how firm it is

Not ready for a rate? The questions buyers ask cover capacity, how long mobilising takes, leases and how billing works.

Read those first

Or call +91 93093 43222 · Monday to Saturday, 9am to 6pm

+91 93093 43222WhatsApp